The Project Schedule list can use a specified Project Calendar list to ensure that the Project Schedule takes note of exception days (e.g. public holidays, weekend working days).
By default, the Project Schedule list uses the Active Calendar and Regional Settings specified on the BrightWork Settings page (and the parameters of these settings are displayed on the settings page); however you can over-ride the site settings and make local Project Schedule specific options available.
The working week is defined on the site's regional settings page.
To make the local options available select Use custom project calendar settings for this list.
Select the items to be recalculated when Recalculate Project Schedule is performed.
The options include:
Automatically calculate Status Indicator for tasks
Automatically calculate Planned Start and Planned Finish dates for tasks
Note:
Unselecting this option causes the Planned Duration to be calculated using the Planned Start and Planned Finish dates.
Automatically calculate % Complete for tasks
Note:
Unselecting this option causes the % Complete to be only automatically updated when the Status is changed to (1) Not Started (set to 0%) or (3) Completed (set to 100%).
Automatically calculate % Work Complete for tasks
Note:
Unselecting this option causes the % Work Complete to be only automatically updated when the Status is changed to (1) Not Started (set to 0%) or (3) Completed (set to 100%).
Automatically calculate Order Number for all items
Select the optional features to include in this project schedule:
Enable tracking of Estimated Duration
This hides the Estimated Duration To Complete and Estimated Duration At Completion columns (and causes Planned Duration to used in calculations where appropriate)
Enable tracking of Estimated Work
This hides the Estimated Work To Complete and Estimated Work At Completion columns
Enable tracking of Estimated Cost
This hides the Estimated Cost To Complete and Estimated Cost At Completion columns
Select Enable background recalculate if you want the Project Schedule list to recalculate automatically.
Note:
This automatic Project Schedule Recalculate feature must be activated from SharePoint Central Admin and the Reschedule timer job settings can be adjusted via stsadm.
This feature must be enabled on a project by project basis, i.e. if enabled, the setting is not preserved when creating a project or template.