Define Working Week

The working week is defined on a site by site basis and is used by the Project Schedule list and Resource Usage Reports to complete their calculations. The default is Monday to Friday. If you wish to define something other than this, follow the steps below.

To define a working week:

  1. Click Site Actions | Site Settings.

  2. Click Regional Settings.

  3. Select the appropriate days in the Define Your Work Week section.

  4. Click OK.

Send feedback on this help.